340 km Hyderabad Regional Ring Road (RRR) expressway project by NHAI is a proposed 4 lane access-controlled road connecting the towns of Sangareddy, Toopran, Choutuppal, Amangal, and Shankarpally.

Hyderabad Regional Ring Road (RRR), a significant infrastructure project in Telangana, India.

Overview

The Hyderabad RRR is a proposed expressway encircling the city of Hyderabad. Here are the key points:

Project Details

  • Phases: The RRR will be developed in two portions:
    • Northern Half: Approximately 164 kilometers, estimated to cost Rs. 9,500 crore. It will connect towns like Sangareddy, Narsapur, Toopran, Gajwel, Yadadri, Pragnapur, Bhongir, and Choutuppal.
    • Southern Half: Approximately 182 kilometers, estimated to cost Rs. 6,480 crore. It will connect Choutuppal, Ibrahimpatnam, Kandukur, Amangal, Chevella, Shankarpally, and Sangareddy.
  • Ownership: The project falls under the National Highways Authority of India (NHAI).
  • Design: Initially, it will be an access-controlled four-lane expressway, but further details will depend on the Detailed Project Report (DPR) recommendations.
  • Status: As of now, the DPR for the northern portion is under preparation1.

Route Map

The RRR will intersect various national highways (NH-44, NH-164, NH-65, NH-765, NH-63) and state highways (SH-1, SH-19). While the official PDF route map is yet to be finalized, the indicative alignment is available

 

 

This new greenfield expressway in Telangana will be developed in 2 parts (northern & southern) under the government’s Bharatmala Pariyojana (BMP) Phase-I program. Telangana Government plans to bear 50% of its land acquisition cost and allocated Rs. 750 crore towards it in its 2021-2022 budget.

  • Total Estimated Cost: Rs. 17,000 crore
  • Project’s Total Length: 340 km
  • Lanes: 4
  • Status: DPR Preparation
  • Deadline: Not Announced
  • Owner: National Highways Authority of India (NHAI)
  • Project Model: Not Announced

The project will be developed in two portions:

Northern half  with a length of approx. 164 km is estimated to cost Rs. 9,500-crore and will connect Sangareddy, Narsapur, Toopran, Gajwel, Yadadri, Pragnapur, Bhongir and Choutuppal.

Southern half with a length of approx. 182 km is estimated to cost Rs. 6,480-crore and will connect Choutuppal, Ibrahimpatnam, Kandukur, Amangal, Chevella, Shankarpally and Sangareddy.

Route Map

Hyderabad Regional Ring Road’s alignment will run roughly 30 km away from the operational 158 km Outer Ring Road (ORR). It will connect various national highways and state highways such as NH-44, NH-164, NH-65, NH-765, NH-63, SH-1, and SH-19.

Regional Ring Road Alignment

Villages in Regional Ring Road Gazette

RRR South Part Proposed Alignment